Construction permits and approvals in Kazakhstan under the EAEU Treaty: a checklist for foreign clients

Aigerim Serikbayeva · August 2026 · 9 min read

Foreign investors in Kazakhstan must navigate a multi-stage permit process that the EAEU Treaty does not simplify. A practical checklist. Make an enquiry.

Foreign companies that assume EAEU membership smooths the path to construction permits and approvals in Kazakhstan under the EAEU Treaty frequently discover the opposite. The Treaty establishes a common economic space across member states but preserves construction permitting as a matter of national competence: Kazakh law governs every stage, from land allocation to commissioning. Investors who arrive expecting mutual recognition of foreign construction licences or simplified approvals typically encounter the full domestic procedure -- with timelines, document standards, and supervisory requirements that differ materially from Russian, Belarusian, or European norms.

This checklist sets out the six principal stages of the construction permit and approval process in Kazakhstan. Each item identifies the substantive requirement, the authority responsible, and the practical risk of non-compliance. It is intended for foreign companies, joint ventures, and in-house counsel managing an inbound construction project in Kazakhstan from inception through to commissioning.

1. Confirm the project category and applicable technical regulations

The first step for any foreign investor is to determine how Kazakh law classifies the intended construction project. Kazakhstan's regulatory framework distinguishes between projects by type (residential, commercial, industrial, infrastructure) and by complexity class, which in turn determines which approvals are mandatory, which supervisory authority takes lead, and what documentation standard applies throughout.

The EAEU Treaty provides for partial harmonisation of technical regulations across member states -- the so-called EAEU technical regulations (Tekhnicheskiye Reglamenty) -- but their scope in construction is limited to specific product and material standards. Procedural requirements for permitting, site supervision, and commissioning remain governed entirely by Kazakh legislation.

Practical note: Foreign investors should obtain a formal written classification determination from the relevant authority before committing to a project programme. Misclassification at the outset frequently causes downstream delays when the supervisory authority applies a higher documentation standard than the investor had anticipated.

Note: Projects meeting the threshold for state expertise review are subject to compulsory submission to the state examination authority before design approval can proceed. Proceeding to site without this examination, where it is required, constitutes a breach of Kazakh construction legislation and may result in suspension of works and administrative liability for the entity responsible.

2. Verify land allocation and title before any design work commences

Construction permitting in Kazakhstan is inseparable from land rights. A foreign company or its Kazakhstani project vehicle must hold a confirmed land-use right -- whether ownership, long-term lease, or a right of temporary paid land use -- before any design documentation can be submitted for approval. The Akimat (local executive authority) is the competent body for land allocation decisions, and its resolution forms the foundation document for all subsequent permit applications.

Foreign legal entities face additional requirements under Kazakh land legislation: direct ownership of land plots for construction purposes is generally restricted, and the standard structure for foreign investors is either a Kazakhstani legal entity that holds the land right, or a long-term lease arrangement.

Practical note: Early confirmation of the land-right structure is essential. Design work undertaken before land rights are formalised risks being unusable if the allocation is refused or modified.

Note: Land rights that are formally allocated but not registered with the relevant state body within the statutory period may be treated as void. Foreign investors unfamiliar with Kazakh registration timelines should build compliance with registration deadlines explicitly into their project schedule -- lapse of a land-right registration can require the entire allocation procedure to restart.

3. Obtain the architectural-planning assignment and design approval

Once land rights are confirmed, the investor must obtain an architectural-planning assignment (APZ -- arkhitekturno-planirovochnoye zadaniye) from the relevant local architecture authority, typically operating under the Akimat. The APZ defines the technical and aesthetic parameters within which the design documentation must be developed. It is not a discretionary document -- submission of design documentation that does not conform to the APZ parameters will result in rejection at the state examination stage.

Design documentation itself must be developed by a licensed Kazakhstani design organisation or by a foreign design organisation holding the applicable Kazakh certification. Foreign investors who engage their home-country architects without verifying Kazakh licensing status regularly encounter refusal at the examination stage and the cost of redesign.

Note: If the project requires state ecological expertise in addition to the standard construction examination -- which is common for industrial and infrastructure projects above certain thresholds -- both examination processes must be completed and positive conclusions obtained before the construction permit application can be lodged. Running these in parallel where permissible can reduce the overall timeline materially; sequential submission when parallel processing is available is a common and costly error.

4. Pass state architectural and construction supervision -- registration and compliance

State Architectural and Construction Supervision (the supervisory authority known colloquially as GASK -- Gosudarstvennyy Arkhitekturno-Stroitelnyy Kontrol) is the central regulatory body for construction oversight in Kazakhstan. Before works commence on site, the project must be registered with the relevant territorial GASK body. This registration triggers an ongoing supervisory obligation: the developer and general contractor are required to maintain a construction log, notify GASK of key works stages, and permit supervisory inspections throughout the construction period.

Foreign investors operating through a Kazakhstani project company should be aware that the obligations imposed by GASK registration fall on the Kazakhstani entity as the permit holder, not on the foreign parent. However, parent-level compliance structures -- particularly for group reporting and insurance -- need to be aligned with GASK's documentation requirements from the outset.

Practical note: Non-notification of GASK at mandatory stages -- including commencement of foundation works and structural frame -- constitutes a standalone violation under Kazakh administrative law, regardless of whether the construction itself is technically compliant. The supervisory timeline imposed by GASK is separate from the construction programme and must be managed in parallel.

Note: Proceeding to superstructure without completing foundation-stage notification and inspection creates a risk that GASK will require opening of completed works for verification. In practice, this risk is not theoretical: GASK has administrative authority to order partial demolition of non-inspected works where inspection records are absent. Foreign project managers who treat GASK notification as a formality rather than a programme constraint routinely encounter this consequence.

5. Lodge the construction permit application -- and understand what it does not cover

The construction permit (razresheniye na stroitelstvo) is the principal regulatory instrument authorising the commencement of works on site. It is issued by the relevant Akimat following confirmation that the design documentation has passed state examination, land rights are formalised, and GASK registration is complete. The permit specifies the scope of authorised works, the validity period, and the conditions attached.

Foreign investors accustomed to jurisdictions where a single permit authorises the full construction programme should note that Kazakh practice commonly requires separate permits or approvals for material variations to the authorised scope, including changes to footprint, height, structural system, or use classification. Scope variations that in other jurisdictions might be managed through a minor amendment procedure can, in Kazakhstan, require a full re-examination and re-permitting cycle.

Practical note: The permit validity period is not automatically extended. Where construction is delayed beyond the authorised period -- whether by supply chain disruption, funding gaps, or regulatory delays in a parallel process -- extension must be applied for before expiry. A lapsed permit cannot be relied upon as authority to continue works; continuation without a valid permit exposes the entity to suspension and administrative liability.

Note: Under Kazakh regulatory practice, the construction permit does not authorise connection to utility networks. Separate approvals from the relevant utility operators -- electricity, gas, water, heat -- must be obtained in parallel with or following the construction permit, and connection agreements must be in place before commissioning can proceed. Investors who do not open utility connection processes until after the construction permit is issued routinely find that commissioning is delayed by utility approval timelines that are entirely outside their control.

6. Register completion and obtain the commissioning act

The final stage in the Kazakh construction approval sequence is the commissioning procedure -- obtaining the act of putting the facility into operation (akt vvoda v ekspluatatsiyu). This document formally concludes the regulatory lifecycle of the construction project and is the prerequisite for registration of the completed building or structure in the state real estate register.

Commissioning requires: confirmation from GASK that all supervisory checkpoints have been passed and the construction log is complete; a positive technical inspection conclusion; and confirmation that utility connections have been completed and tested. In practice, a pre-commissioning inspection by GASK is standard, and any outstanding deficiencies identified at that inspection must be remedied before the commissioning act is issued.

Note: The commissioning act is also the document that activates the investor's right to register the completed asset. Without it, the asset cannot be registered in the Kazakhstani real estate register -- meaning that the investor holds no formally recognised property right in the completed building. A building that is physically complete but lacks a commissioning act is not a bankable or transferable asset under Kazakh law, and this gap has caused material complications for foreign investors seeking project financing or a sale of the completed development.

Frequently asked questions

Q: Does the EAEU Treaty allow a foreign company to bypass Kazakh construction licensing requirements?

A: No. The EAEU Treaty establishes a common economic space and provides for mutual recognition of certain professional qualifications and harmonised technical regulations in defined product areas, but it does not harmonise member states' construction permitting procedures. Kazakhstan retains full national competence over its construction licensing and approval regime. A foreign company -- including one established in Russia, Belarus, Armenia, or Kyrgyzstan -- cannot rely on the Treaty to avoid or substitute for any stage of the Kazakh construction permit procedure. The applicable legal framework at every stage is Kazakh national legislation, administered by Kazakh authorities.

Q: Are any construction projects in Kazakhstan exempt from the full permit procedure?

A: Kazakh legislation does provide for simplified or modified procedures for certain categories of lower-complexity works -- typically small auxiliary structures, temporary construction, and certain types of refurbishment that do not affect the structural elements or use classification of an existing building. However, these exemptions are defined by reference to specific thresholds and categories established under Kazakh law. Foreign investors should not assume that any proposed construction activity falls within an exemption category without a formal determination from the relevant authority. In practice, projects of the scale and character typically undertaken by foreign corporate investors rarely qualify for simplified procedures.

Q: What happens if construction proceeds without the required Kazakh approvals?

A: Commencing or continuing construction without the requisite approvals -- including construction permit, GASK registration, and compliance with state examination requirements -- exposes the responsible entity to administrative liability under Kazakh law, which may include suspension of works by the supervisory authority, mandatory demolition of unauthorised construction in certain circumstances, and financial penalties. Beyond the regulatory consequences, a building constructed without the proper approvals cannot be commissioned, which means the asset cannot be registered and cannot be sold, mortgaged, or used as security. Foreign investors who proceed speculatively, on the assumption that approvals will follow, regularly find that retrospective regularisation -- where it is available at all -- is significantly more costly and time-consuming than front-end compliance.

Practitioner note

This briefing is general information and does not constitute legal advice. For advice on a specific matter, write in confidence to info@vetrovpartners.com.

Facing a matter like this?

Our team advises foreign clients on exactly these questions across Russia and the EAEU region. Initial 30-minute consultation — complimentary.

Make an enquiry