Novosibirsk · Russian-qualified counsel Recognised by Pravo-300 · Best Lawyers · Kommersant
Uzbekistan · Analysis

Construction permits and approvals in Uzbekistan under the Law on Subsoil: what in-house counsel need to know

Nodira Yusupova · August 2026 · 9 min read

Uzbekistan's Law on Subsoil adds a distinct approval layer for foreign-investor construction projects. What in-house counsel must verify. Make an enquiry.

Uzbekistan's construction permitting regime has become materially more complex for foreign investors since the Law on Subsoil consolidated and restructured the regulatory framework governing land-use, underground resources, and the surface activities connected to them. For in-house counsel managing a foreign company's Uzbek operations or a new market-entry project, understanding where the standard construction permit process intersects with subsoil-use approvals is not a preliminary question — it is the threshold question. Failures at this intersection have delayed project timelines by months and, in some instances, triggered mandatory remediation or re-tendering obligations. This guide sets out the five-step approval sequence that in-house counsel should map before any ground is broken.

What to prepare before you begin

The following documentation and assessments should be in place before initiating any permit application. Missing items at submission typically result in a suspension rather than a rejection, but suspension carries its own timeline risk.

Note: If the cadastral record or geological screening reveals any overlap with a subsoil licence area — whether active or reserved — the subsoil-coordination track becomes mandatory before the standard construction permit can be issued. Triggering this track after submission wastes the filing fee and restarts the clock.

Step 1 — Confirm the land-use classification and subsoil status

The first and most frequently underestimated step is a dual-track classification check. Under Uzbekistan's land code and the Law on Subsoil, land plots are classified both by surface use (agricultural, industrial, urban development, special-purpose) and by subsoil status (open, licensed, reserved, restricted). These are independent registries maintained by different state bodies.

For a foreign investor, in-house counsel should confirm both classifications formally — not merely by inspecting the land allocation certificate. The subsoil registry is maintained by the State Committee on Geology and Mineral Resources (Goskomgeo), while surface land records sit with the State Committee on Land Resources, Geodesy, Cartography and State Cadastre. A plot can carry a clean surface classification while sitting above a licensed subsoil area. The Law on Subsoil gives subsoil-use rights a form of priority that can constrain surface development significantly.

Practical note: in Uzbekistan's construction practice, foreign investors have encountered situations where a land allocation certificate was issued by a khokimiyat without cross-referencing the subsoil registry. This is a process gap, not a legal authorisation. Counsel should not treat the allocation certificate as a subsoil-status clearance.

Step 2 — Does the Law on Subsoil require a separate subsoil-use authorisation?

The Law on Subsoil distinguishes between construction that incidentally affects the subsoil (shallow foundations, standard utility connections) and construction that constitutes subsoil use in the regulatory sense (deep excavation, underground structures, extraction of any mineral or groundwater, tunnelling). The distinction is consequential: the latter category requires a subsoil-use authorisation that is procedurally separate from, and must precede, the standard construction permit.

The competent authority for subsoil-use authorisations is Goskomgeo, operating under rules that set out the form of licence, the permissible scope of the authorisation, and the conditions attaching to it. Key points for in-house counsel:

"The Law on Subsoil in Uzbekistan has effectively created a second permitting sequence that sits upstream of the standard construction approval — one that foreign investors, accustomed to a single-track regime, consistently discover later than advisable." — Nodira Yusupova, Contributing Regional Analyst — Uzbekistan, Vetrov & Partners

Step 3 — Navigate the construction permit process through the Uzstroiinspeksiya

The State Inspectorate for Construction and Technical Supervision (Uzstroiinspeksiya) is the principal permitting body for construction permits in Uzbekistan. For projects of a scale or type that require a full state examination of project documentation (gosudarstvennaya ekspertiza), the examination must be completed before the permit is issued. This examination covers technical, environmental, and — where applicable — subsoil-coordination compliance.

The sequence for foreign investors in practice:

Note: The state examination (ekspertiza) is not a formality. For projects involving foreign capital above certain thresholds, or projects in sectors designated as strategic, an extended review process applies. In-house counsel should build a realistic timeline that reflects examination duration — not just permit-issuance duration. The two are counted separately.

Step 4 — Environmental approvals and special-sector overlays

For projects in mining, energy, agri-industrial, or infrastructure sectors, the standard permitting sequence is supplemented by sector-specific regulatory overlays. The Law on Subsoil intersects most acutely with extractive-sector projects, but its reach extends to any project that materially affects the subsurface environment.

Environmental approval (ekologicheskaya ekspertiza) is required for a defined category of projects, assessed by the Ministry of Ecology. Where the project triggers both a subsoil-use authorisation and an environmental examination, the two processes are nominally parallel but practically interdependent — the environmental examination will review the subsoil-use conditions, and a material change in the subsoil authorisation after environmental approval may require re-examination.

For foreign investors, additional points under Uzbekistan's regulation foreign company framework:

Step 5 — Commissioning approvals and ongoing compliance under the subsoil-use licence

A construction permit authorises construction. It does not authorise use. The commissioning stage — formally the acceptance and commissioning of a completed facility (priëmka v ekspluatatsiyu) — is a separate approval process in Uzbekistan, conducted by Uzstroiinspeksiya with potential involvement from Goskomgeo where the subsoil-use authorisation conditions require a completion verification.

Where a subsoil-use licence was required under Step 2, the licence conditions typically include:

For in-house counsel, the practical implication is that ongoing compliance with the subsoil-use licence runs in parallel with the construction phase and does not end at permit issuance. Appointing a responsible officer within the Uzbek entity to manage licence condition compliance — and documenting that compliance — reduces exposure to licence suspension at the commissioning stage.

Note: A commissioning certificate cannot be issued where there are outstanding non-compliance notices under the subsoil-use licence. In practice, this means that a compliance failure at any stage during construction can block the commissioning approval for the entire facility — regardless of construction quality. In-house counsel should ensure that subsoil-use licence conditions are tracked as live compliance obligations throughout the project, not as background documentation.

Frequently asked questions

Q: Does every construction project in Uzbekistan require a subsoil-use authorisation under the Law on Subsoil?

A: No. The Law on Subsoil applies a threshold test: construction that involves only shallow works and does not affect any licensed or regulated subsoil area typically proceeds under the standard construction permit without a separate subsoil authorisation. The obligation to obtain a subsoil-use authorisation arises where the project involves deep excavation, underground structures, the extraction of any mineral resource or significant groundwater volume, or is located on a plot that overlaps with a licensed or reserved subsoil area. In-house counsel should treat the preliminary classification check (Step 1) as the diagnostic that determines whether the subsoil track applies — not the construction permit application itself.

Q: How long does the full approval process typically take for a foreign investor's construction project in Uzbekistan?

A: Where the project is straightforward and the subsoil track does not apply, the combined land confirmation, state examination, and construction permit process typically runs between three and six months from the point of complete documentation. Where the subsoil-use authorisation track is engaged, total elapsed time from initial classification check to construction permit issuance commonly extends to nine to fourteen months, depending on the complexity of the subsoil conditions and the sector. Environmental examination adds a further variable. In practice, for cross-border Uzbekistan Russia projects coordinated from abroad, timeline slippage most commonly results from incomplete documentation at the state examination stage — a gap that early legal advice on documentation requirements avoids.

Q: Can a foreign company hold the construction permit and subsoil-use authorisation directly, or must a local Uzbek entity be the permit holder?

A: Under Uzbekistan's regulation framework for foreign companies, both the construction permit and the subsoil-use authorisation are typically issued to the Uzbek legal entity or accredited branch that holds the land rights for the project. A foreign parent company holding the land allocation directly would be unusual and, for most project types, not available as a structure. In-house counsel should confirm the entity structure before any permit application is filed, as the permit-holding entity must match the entity named in the land allocation documentation. Restructuring the holding entity after permit issuance is possible but administratively costly and time-consuming.

Practitioner note

This briefing is general information and does not constitute legal advice. For advice on a specific matter, write in confidence to info@vetrovpartners.com.

Facing a matter like this?

Our team advises foreign clients on exactly these questions across Russia and the EAEU region. Initial 30-minute consultation — complimentary.

Make an enquiry